Time Estimates |
Uses three estimates (optimistic, pessimistic, most likely) |
Uses a single, fixed time estimate |
Uncertainty |
Designed to handle uncertainty |
Assumes fixed, deterministic durations |
Focus |
Focuses on probabilistic scheduling |
Focuses on critical path and project duration |
Use Case |
Best for uncertain, complex projects (e.g., R&D, technology) |
Best for predictable projects (e.g., construction) |
Critical Path |
Identifies critical path, but the main focus is on time estimates |
Strong emphasis on identifying and managing the critical path |
Risk Management |
Considers uncertainty and variability |
Assumes known durations, less focus on risk |